Sample deliverable: demonstration data. This is actual rendered output from the CPP forensic toolkit, run on a fictional project. The methodology, detectors and calculations are the production ones; the activity codes, RFI numbers, change orders and party assignments are illustrative and were chosen to exercise the full range of forensic detectors. Nothing here is a real project, a real party, or a real claim. See all sample deliverables · criticalpathpartners.ca
Skip to main content
CPP
Critical Path PartnersForensic Schedule Analysis
Schedule Health Review

Schedule Health DashboardDCMA 14-Point Assessment & Quality Compliance Analysis

Project
Ontario Community College
Data date
01-Jul-2025
Baseline
01-Apr-2025
Activities
405
Overall quality grade
F
Critical
remediation advised
Status
RED
DCMA-14
5 / 13
Compliance
38%
A-01

Executive Summary

AI narrative · health score · intelligence
Key Findings

The Ontario Community College schedule passes 5 of 13 scored DCMA criteria, earning an overall grade of F (38% compliance) with a RED status band. Criteria clearing their thresholds: C1, C4, C5, C7, C12.

The failing criteria are C2 Leads, C3 Lags, C6 High Float, C8 High Duration, C9 Valid Dates, C11 Missed Tasks, C13 CPLI, C14 BEI. Both forward-looking indices read CPLI 0.93 and BEI 0.58, and the schedule is trending toward +21 working-day overrun to 30-Sep-2026.

Passed
5
Failed
8
Compliance
38%
Finish Var.
+21 WD
Health Score
38%Grade F
RED
Trend watch · BEI 0.58, CPLI 0.93
finish drift +21 WD vs baseline
A-01b

Executive Schedule Intelligence

issues · actions · summary
Critical Issues Requiring Attention
  • Leads (7), 7 leads found (C2).
  • Lags (10.6%), 69 of 653 relationships (10.6%) | 1 exceed 44 days (C3).
  • High Float (53% (152)), 152 activities with high float (53.0%) (C6).
  • High Duration (13.2% (38)), 38 activities with high duration (13.2%) (C8).
  • Valid Dates (103), 103 activities with invalid dates (26.1%; 0 forecast, 103 actual) | Status date: 2025-07-01 | Latest actual: 2025-09-16 (+54 wd) | Actual>DD: start 78, finish 80 (C9).
  • Missed Tasks (38), Missed: 38/43 (88.4%) | Missing baseline IDs from current: 0 (C11).
  • CPLI (0.93), CPLI: 0.934 | Contract: 2026-08-31 (AUTO: A4260, Total Completion) | Forecast: 2026-09-30 (AUTO: A4260, Total Completion) | Float: -21d (C13).
  • BEI (0.58), BEI: 0.581 (25 complete / 43 planned complete) (C14).
Priority Actions
  • Resolve Leads (C2): Negative-lag (lead) relationships.
  • Resolve Lags (C3): Excessive lags on relationships.
  • Resolve High Float (C6): Activities with > 44 days of total float.
  • Resolve High Duration (C8): Activities longer than 44 working days.
  • Resolve Valid Dates (C9): Activities with invalid actual or forecast dates.
  • Resolve Missed Tasks (C11): Activities that should have finished by the data date and did not.
  • Resolve CPLI (C13): CPLI below the 0.95 DCMA investigation flag.
  • Resolve BEI (C14): BEI below 0.95, falling behind baseline pace.
A-01.1

Basis of Measurement

how to read these figures & what has been validated
Basis of measurementHow to read the numbers in this report
Day unit
Working days
Every day count in this assessment is in working days. Where a criterion threshold is written in calendar days in DCMA-14, the computed figure is stated in working days alongside.
Calendar
The activity’s own P6 calendar
Durations and float are read as the source scheduler computed them, on each activity’s assigned calendar. This screen does not recompute the network.
Date fields read
P6 Start and Finish columns only
Float basis
Total float as computed by the source scheduler
Taken from the file as submitted. No forward or backward pass is re-run, so a stale or overridden float value is reported as it stands rather than corrected.
Excluded
Level-of-effort and WBS-summary activities
Excluded from the criteria where the check does not apply, per DCMA-14.
This is a screening assessment, and its validation boundary is narrower than the engine’s
The figures here are counts, percentages and float in days. No signed variance against a contract is reported, so there is no loss-direction convention to apply; where a forensic deliverable is needed, those skills state their own sign convention on their own page one.
What has been validated: the CPP CPM engine is cross-validated against Primavera P6 23.12 (46 fixtures, 1,009 executed field comparisons, zero disagreements; history and limits at criticalpathpartners.ca/validation.html), and that cross-validation covers the ENGINE. It does not cover this DCMA-14 screen, which is computed in the browser from the file as submitted. These results have not been reviewed against the contract, the project records, or an AACE 29R-03 source validation, and they are not a delay analysis or an entitlement finding.
A-02

Key Performance Metrics

14-criteria roll-up
Criteria Passed
5
of 13 scored criteria
Criteria Failed
8
requires attention
Compliance Rate
38%
overall quality score
Overall Rating
F
assessment grade
A
≥90 Excellent
B
≥75 Good
C
≥60 Acceptable
D
≥45 Below Std
F
<45 Critical
A-03

DCMA 14-Point Assessment

13 scored · 5 PASS / 8 FAIL · Grade F
Logic & FlowC1–C4 · 2 PASS / 2 FAIL
C1
Logic
Activities missing a predecessor or successor
Missing Logic · ≤5%
2.4% (7)
PASS
3 w/o predecessors (1.0%), 5 w/o successors (1.7%)
C2
Leads
Relationships with a negative lag (lead)
Leads · target 0
7
FAIL
7 leads found see register A-06
C3
Lags
Relationships carrying a positive lag
Rels w/ Lag · ≤5%
10.6%
FAIL
69 of 653 relationships (10.6%) | 1 exceed 44 days see register A-06
C4
Relationship Types
Share of links that are Finish-to-Start
FS Share · ≥90%
94% FS
PASS
Total: 653 | FS: 614 (94.0%), SS: 30 (4.6%), FF: 9 (1.4%), SF: 0 (0.0%)
Constraints & FloatC5–C7 · 2 PASS / 1 FAIL
C5
Hard Constraints
Mandatory / fixed-date constraints in the network
Hard Constraints · ≤5%
0
PASS
0 hard constraints (0.0%)
C6
High Float
Incomplete activities with total float > 44 wd
High Float · ≤5%
53% (152)
FAIL
152 activities with high float (53.0%) see register A-06
C7
Negative Float
Activities with total float below zero
Negative Float · target 0
0
PASS
0 activities with negative float
Resources & ProgressC9–C11 · 2 FAIL / 1 N/A
C9
Valid Dates
Forecast dates before, or actual dates after, the data date
Invalid Dates · target 0
103
FAIL
103 activities with invalid dates (26.1%; 0 forecast, 103 actual) | Status date: 2025-07-01 | Latest actual: 2025-09-16 (+54 wd) | Actual>DD: start 78, finish 80 see register A-06
C10
Resources
Activities with a resource or cost loaded
Resourced · 100%
N/A
N/A
Not scored - TASKRSRC section not found in XER export. (282 eligible activities ≥1d)
C11
Missed Tasks
Activities that slipped past baseline finish
Missed Tasks · ≤5%
38
FAIL
Missed: 38/43 (88.4%) | Missing baseline IDs from current: 0 see register A-06
PerformanceC8–C14 · 1 PASS / 3 FAIL
C8
High Duration
Incomplete activities with duration > 44 wd
High Duration · ≤5%
13.2% (38)
FAIL
38 activities with high duration (13.2%) see register A-06
C12
Critical Path Test
Screening only: connected, unbroken critical chain. NOT the DCMA +1-day perturbation test
Critical Path
35 activities
PASS
Network OK (finish reachable; orphans 8/287 = 2.8%; critical network 97.1%)
C13
CPLI
Critical Path Length Index, pace to finish
CPLI · ≥0.95
0.93
FAIL
CPLI: 0.934 | Contract: 2026-08-31 (AUTO: A4260, Total Completion) | Forecast: 2026-09-30 (AUTO: A4260, Total Completion) | Float: -21d
C14
BEI
Baseline Execution Index, tasks earned vs planned
BEI · ≥0.95
0.58
FAIL
BEI: 0.581 (25 complete / 43 planned complete)
Thresholds per the DCMA 14-Point Assessment · quality compliance analysis5 PASS  /  8 FAIL  →  Grade F · 38% · RED
A-04

DCMA-14 Status by Criterion

14 criteria · PASS / FAIL
Per-criterion compliance, full result vs threshold toleranceC1 → C14
C1 · LogicC2 · LeadsC3 · LagsC4 · Relationship TypesC5 · Hard ConstraintsC6 · High FloatC7 · Negative FloatC8 · High DurationC9 · Valid DatesC10 · ResourcesC11 · Missed TasksC12 · Critical Path TestC13 · CPLIC14 · BEIPASS · 2.4% (7)FAIL · 7FAIL · 10.6%PASS · 94% FSPASS · 0FAIL · 53% (152)PASS · 0FAIL · 13.2% (38)FAIL · 103N/AFAIL · 38PASS · 35 activitiesFAIL · 0.93FAIL · 0.58
PASS · within tolerance FAIL · exceeds threshold5 PASS  /  8 FAIL
A-05

Baseline vs Current Comparison

task · schedule · variance
Task Metrics
Baseline Tasks327
Current Tasks405
Tasks Added+78
Scope Growth23.9%
Schedule Metrics
Baseline Start01-Apr-2025
Current Start01-Apr-2025
Baseline Finish31-Aug-2026
Current Finish30-Sep-2026
Variance Analysis
Start Delay0 WD
Finish Variance+21 WD
Duration Variance+21 WD
Scope Growth+23.9%
A-06

Failure Analysis & Registers

8 failing criteria · severity profile · full activity registers
C2Leads Register, all flagged activities
7 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A2290Existing Structure Under Pinning1.4.5.1 Phase 1 - Early Works15-Jul-2025Lead (d): 2Has 2.0d lead from "Demolition of Existing Vestibule F100"
A2650Install Level 2 & 3 Decking1.4.5.3 Phase 3 - Building Erection14-Nov-2025Lead (d): 5Has 5.0d lead from "Erect Structural Steel"
A3580Mech. & Plumbing rough-ins1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 322-Apr-2026Lead (d): 15Has 15.0d lead from "Mech. & Plumbing rough-ins"
A3290Mech. & Plumbing rough-ins1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 115-Apr-2026Lead (d): 5Has 5.0d lead from "New partition framing"
A3180Roof Inspection1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing09-Mar-2026Lead (d): 1Has 1.0d lead from "Install Built-up Roof"
A2620Structural Steel Inspection1.4.5.3 Phase 3 - Building Erection31-Oct-2025Lead (d): 1Has 1.0d lead from "Erect Structural Steel"
A2580Underground Drainage1 Phase 2 - Foundation Work07-Nov-2025Lead (d): 10Has 10.0d lead from "Erect Structural Steel"
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion. Full paths are in the tooltip and the CSV export.
C3Lags Register, all flagged activities
69 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A1370xMetal Shelving1.2 Shop Drawings23-Jun-2025Lag (d): 60Lag of 60.0d from "Subcontract Award" exceeds 44 work days
A1060Foundation Concrete Rebar Shop Drawing1.2 Shop Drawings08-Jul-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1070Foundation Concrete Mix Design1.2 Shop Drawings25-Jun-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1080Bentonite Waterstop Data Sheet1.2 Shop Drawings02-Jul-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1090Masonry and Mortar Samples & Data Sheets1.2 Shop Drawings18-Aug-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)1.2 Shop Drawings14-Jul-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1120Cold-formed Metal Framing Shop Drawings1.2 Shop Drawings23-Jul-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1130Misc. Metals Shop Drawings1.2 Shop Drawings02-Oct-2025Lag (d): 10Has positive lag of 10.0d from "Structural Steel Framing and Steel Deck Shop Drawings (R0)" (lag usage exceeds 5%)
A1140Millwork Shop Drawings1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1150Built-up Roofing Shop Drawings1.2 Shop Drawings09-Jul-2025Lag (d): 15Has positive lag of 15.0d from "Subcontract Award" (lag usage exceeds 5%)
A1160TPO Roofing Shop Drawings1.2 Shop Drawings26-Aug-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1170Air Barrier System Data Sheet and Mockup1.2 Shop Drawings09-Jul-2025Lag (d): 15Has positive lag of 15.0d from "Subcontract Award" (lag usage exceeds 5%)
A1180Exterior Wall Cladding Shop Drawings1.2 Shop Drawings05-Sep-2025Lag (d): 40Has positive lag of 40.0d from "Subcontract Award" (lag usage exceeds 5%)
A1190Fire-resistive Material Data Sheet1.2 Shop Drawings09-Jul-2025Lag (d): 15Has positive lag of 15.0d from "Subcontract Award" (lag usage exceeds 5%)
A1200Hollow Metal Frames & Doors Shop Drawings1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1210Interior Aluminum Screen1.2 Shop Drawings20-Aug-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1220Flush Wood Doors Sample1.2 Shop Drawings27-Aug-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1230Coiling Doors1.2 Shop Drawings21-Aug-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1240Aluminum Framed Glazing System Shop Drawings1.2 Shop Drawings06-Aug-2025Lag (d): 35Has positive lag of 35.0d from "Subcontract Award" (lag usage exceeds 5%)
A1250Finished Hardware Schedule1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1260Stud framing and Gypsum Board Data Sheets1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1270Tiling Data sheet and samples1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1280ACT Data sheet and Sample1.2 Shop Drawings27-Aug-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1290Suspended Metal Soffits1.2 Shop Drawings04-Sep-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1300Flooring Data Sheets and Samples1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1310Paint Drawdowns1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1320Washroom accessories and Partitions Shop Drawings1.2 Shop Drawings29-Jul-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1330Fall Arrest Anchors and Horizontal Lines1.2 Shop Drawings29-Sep-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A1340Hydraulic Lift Shop Drawings1.2 Shop Drawings09-Jul-2025Lag (d): 20Has positive lag of 20.0d from "Subcontract Award" (lag usage exceeds 5%)
A1350Sprinkler & Standpipe Shop Drawings1.2 Shop Drawings16-Jul-2025Lag (d): 20Has positive lag of 20.0d from "Subcontract Award" (lag usage exceeds 5%)
A1610Concrete Mix for Hardscapes1.2 Shop Drawings06-Aug-2025Lag (d): 35Has positive lag of 35.0d from "Subcontract Award" (lag usage exceeds 5%)
A1620Landscape Shop Drawings1.2 Shop Drawings06-Aug-2025Lag (d): 35Has positive lag of 35.0d from "Subcontract Award" (lag usage exceeds 5%)
A3460Electrical, FA & Comms rough-ins1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 201-May-2026Lag (d): 2Has positive lag of 2.0d from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%)
A3300Electrical, FA & Comms rough-ins1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 121-Apr-2026Lag (d): 2Has positive lag of 2.0d from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%)
A3590Electrical, FA & Comms rough-ins1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 308-May-2026Lag (d): 2Has positive lag of 2.0d from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%)
A3480Blocking Installation1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 206-May-2026Lag (d): 3Has positive lag of 3.0d from "Electrical, FA & Comms rough-ins" (lag usage exceeds 5%)
A3610Blocking Installation1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 315-May-2026Lag (d): 5Has positive lag of 5.0d from "Electrical, FA & Comms rough-ins" (lag usage exceeds 5%)
A1110Structural Reinforcement + Decking Shop Drawings1.2 Shop Drawings01-Aug-2025Lag (d): 5Has positive lag of 5.0d from "Subcontract Award" (lag usage exceeds 5%)
A1030IFC Drawings Released1.1 Preconstruction15-May-2025Lag (d): 7Has positive lag of 7.0d from "Contract Award" (lag usage exceeds 5%)
A4240Minor Deficiencies & Touch-ups1.4 Construction / 1.4.8 Closeout and Commissioing30-Sep-2026Lag (d): 2Has positive lag of 2.0d from "Substantial Performance" (lag usage exceeds 5%)
A136023 82 19 - Fan Coil Units (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A137023 74 13 - Air Handling Units (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings21-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A138023 21 23 - Pumps (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings04-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A139023 25 00 - Buffer Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A140023 21 16 - Air Separator1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A141023 21 16 - Expansion Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A142023 57 00 - Heat Exchangers1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A143022 33 00 - Electric Domestic Water Heaters1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A144023 81 26 - Split System1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings30-Jun-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A145022 13 29 - Sump Pumps (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings02-Jun-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A146023 25 00 - Water Treatment (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings14-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A148023 00 00 - Exhaust Fans (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings22-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A149023 00 00 - Unit Heater1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings22-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A150023 52 16 - Heating Boilers1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings21-Oct-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A151023 00 00 - Wall Fin Heater1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A152023 74 13 - Air Source Heat Pump1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings17-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A153020 05 10 - Electric Heat Tracing (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A154022 40 00 - Plumbing Fixtures (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings31-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings08-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A156026 50 00 - Emergency Lighting & Exit Signs1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings29-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings22-Jul-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A158026 50 00 - Lighting Fixtures1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings18-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A159026 09 23 - Lighting Control (R0)1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings18-Aug-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings17-Jun-2025Lag (d): 10Has positive lag of 10.0d from "Subcontract Award" (lag usage exceeds 5%)
A1130Misc. Metals Shop Drawings1.2 Shop Drawings02-Oct-2025Lag (d): 10Has positive lag of 10.0d from "Structural Steel Framing and Steel Deck Shop Drawings (R1)" (lag usage exceeds 5%)
A1130Misc. Metals Shop Drawings1.2 Shop Drawings02-Oct-2025Lag (d): 10Has positive lag of 10.0d from "Structural Steel Framing and Steel Deck Shop Drawings (R2)" (lag usage exceeds 5%)
A1280.1ACB Data sheet and Sample1.2 Shop Drawings04-Sep-2025Lag (d): 30Has positive lag of 30.0d from "Subcontract Award" (lag usage exceeds 5%)
A2550Form and Pour Grade Beams1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work30-Sep-2025Lag (d): 3Has positive lag of 3.0d from "Backfilling to U/S of Grade Beams (GL AA)" (lag usage exceeds 5%)
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion. Full paths are in the tooltip and the CSV export.
C6High-Float Register, incomplete activities with total float > 44 wd
152 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishTotal Float (wd)Issue
A3850Foundations1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction23-Feb-202657Total float of 57d exceeds 44 days
A3860Concrete Vertical Piers1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction02-Mar-202657Total float of 57d exceeds 44 days
A3870Removal of Existing Facade for Tie In1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction05-Mar-202657Total float of 57d exceeds 44 days
A3880Structural Steel erection including expansion plates 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction26-Mar-202657Total float of 57d exceeds 44 days
A3890Envelope 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction30-Apr-202657Total float of 57d exceeds 44 days
A3900Interior M&E Rough in 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction14-May-202657Total float of 57d exceeds 44 days
A3910Interior Finishes1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction15-May-202657Total float of 57d exceeds 44 days
A4150New Exterior Paved Areas and Sidewalks 1.4 Construction / 1.4.7 Exterior Works29-May-202658Total float of 58d exceeds 44 days
A4160Landscape Installations1.4 Construction / 1.4.7 Exterior Works12-Jun-202658Total float of 58d exceeds 44 days
A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation03-Apr-202661Total float of 61d exceeds 44 days
A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation20-Mar-202676Total float of 76d exceeds 44 days
A2890L1 Masonry Wall Installation1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation20-Jan-2026158Total float of 158d exceeds 44 days
A2770L1 Masonry Wall installation1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation31-Dec-2025166Total float of 166d exceeds 44 days
A2840L1, L2, L3 Exterior Glazing Installation (W05)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation13-Mar-202681Total float of 81d exceeds 44 days
A2960L2 & L3 Cladding Installation (EW2)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation19-May-202676Total float of 76d exceeds 44 days
A2870L1, L2 & L3 Cladding Installation (EW2a)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation11-May-202681Total float of 81d exceeds 44 days
A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation13-Mar-202676Total float of 76d exceeds 44 days
A3040L2 & L3 Cladding Installation (EW2)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation11-May-202676Total float of 76d exceeds 44 days
A3050Horizontal Shading Louvers1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation19-May-202676Total float of 76d exceeds 44 days
A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation09-Jun-202661Total float of 61d exceeds 44 days
A3740Millwork Installation1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes02-Jul-202650Total float of 50d exceeds 44 days
A3520Door and Hardware Installation1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 211-May-202646Total float of 46d exceeds 44 days
A4540Interior Demolition 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo24-Dec-2025193Total float of 193d exceeds 44 days
A3940Existing Slab Removal and Trenching1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation28-Oct-2025219Total float of 219d exceeds 44 days
A4010Underground Plumbing Rough-ins1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)16-Jul-2025135Total float of 135d exceeds 44 days
A4760Trench Backfill1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)23-Jul-2025135Total float of 135d exceeds 44 days
A1140Millwork Shop Drawings1.2 Shop Drawings29-Jul-2025228Total float of 228d exceeds 44 days
A1170Air Barrier System Data Sheet and Mockup1.2 Shop Drawings09-Jul-2025144Total float of 144d exceeds 44 days
A1180Exterior Wall Cladding Shop Drawings1.2 Shop Drawings05-Sep-2025172Total float of 172d exceeds 44 days
A1200Hollow Metal Frames & Doors Shop Drawings1.2 Shop Drawings29-Jul-2025162Total float of 162d exceeds 44 days
A1210Interior Aluminum Screen1.2 Shop Drawings20-Aug-2025133Total float of 133d exceeds 44 days
A1240Aluminum Framed Glazing System Shop Drawings1.2 Shop Drawings06-Aug-2025131Total float of 131d exceeds 44 days
A1250Finished Hardware Schedule1.2 Shop Drawings29-Jul-2025132Total float of 132d exceeds 44 days
A1260Stud framing and Gypsum Board Data Sheets1.2 Shop Drawings29-Jul-202595Total float of 95d exceeds 44 days
A1270Tiling Data sheet and samples1.2 Shop Drawings29-Jul-2025213Total float of 213d exceeds 44 days
A1300Flooring Data Sheets and Samples1.2 Shop Drawings29-Jul-2025183Total float of 183d exceeds 44 days
A1310Paint Drawdowns1.2 Shop Drawings29-Jul-2025212Total float of 212d exceeds 44 days
A1320Washroom accessories and Partitions Shop Drawings1.2 Shop Drawings29-Jul-2025228Total float of 228d exceeds 44 days
A1350Sprinkler & Standpipe Shop Drawings1.2 Shop Drawings16-Jul-2025191Total float of 191d exceeds 44 days
A1610Concrete Mix for Hardscapes1.2 Shop Drawings06-Aug-2025238Total float of 238d exceeds 44 days
A1620Landscape Shop Drawings1.2 Shop Drawings06-Aug-2025203Total float of 203d exceeds 44 days
A1670Masonry and Mortar1.3 Procurement25-Aug-2025253Total float of 253d exceeds 44 days
A1700Cold-formed Metal Framing 1.3 Procurement07-Aug-202594Total float of 94d exceeds 44 days
A1720Millwork 1.3 Procurement09-Oct-2025228Total float of 228d exceeds 44 days
A1730Built-up Roofing 1.3 Procurement21-Aug-2025127Total float of 127d exceeds 44 days
A1740TPO Roofing (Bridge)1.3 Procurement08-Oct-2025173Total float of 173d exceeds 44 days
A1750Air Barrier System1.3 Procurement23-Jul-2025144Total float of 144d exceeds 44 days
A1760Exterior Wall Cladding1.3 Procurement01-Dec-2025172Total float of 172d exceeds 44 days
A1770Fire-resistive Material 1.3 Procurement07-Aug-2025138Total float of 138d exceeds 44 days
A1780Hollow Metal Frames1.3 Procurement25-Sep-2025162Total float of 162d exceeds 44 days
A1800Interior Aluminum Screens1.3 Procurement29-Dec-2025133Total float of 133d exceeds 44 days
A1810Flush Wood Doors 1.3 Procurement12-Dec-2025127Total float of 127d exceeds 44 days
A1820Coiling Doors1.3 Procurement14-Jan-2026106Total float of 106d exceeds 44 days
A1830Aluminum Framed Glazing Systems1.3 Procurement28-Nov-2025131Total float of 131d exceeds 44 days
A1840Finished Hardware 1.3 Procurement05-Dec-2025132Total float of 132d exceeds 44 days
A1850Stud framing & gypsum board1.3 Procurement06-Aug-202595Total float of 95d exceeds 44 days
A1860Tiling 1.3 Procurement11-Sep-2025213Total float of 213d exceeds 44 days
A1870ACT & ACB 1.3 Procurement17-Oct-2025156Total float of 156d exceeds 44 days
A1890Flooring 1.3 Procurement24-Oct-2025183Total float of 183d exceeds 44 days
A1900Paint Drawdowns1.3 Procurement13-Aug-2025212Total float of 212d exceeds 44 days
A1910Washroom accessories and Partitions 1.3 Procurement04-Sep-2025228Total float of 228d exceeds 44 days
A1930Hydraulic Lift 1.3 Procurement01-Dec-2025141Total float of 141d exceeds 44 days
A1940Sprinkler & Standpipe Shop Drawings1.3 Procurement07-Aug-2025191Total float of 191d exceeds 44 days
A2200Concrete for Hardscape1.3 Procurement13-Aug-2025238Total float of 238d exceeds 44 days
A2210Landscape (unit pavers, furniture, etc)1.3 Procurement31-Oct-2025203Total float of 203d exceeds 44 days
A4530Electrical and Mechanical Make Safe1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo10-Dec-2025193Total float of 193d exceeds 44 days
A1790Hollow Metal Doors1.3 Procurement24-Oct-2025162Total float of 162d exceeds 44 days
A2850Exterior Cladding Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation16-Mar-202681Total float of 81d exceeds 44 days
A2820Glazing Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation30-Dec-202591Total float of 91d exceeds 44 days
A2830Glazing Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation27-Jan-202691Total float of 91d exceeds 44 days
A2860Exterior Cladding Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation13-Apr-202681Total float of 81d exceeds 44 days
A2910Glazing Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation14-Jan-202676Total float of 76d exceeds 44 days
A2920Glazing Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation10-Feb-202676Total float of 76d exceeds 44 days
A2940Exterior Cladding Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation23-Mar-202676Total float of 76d exceeds 44 days
A2950Exterior Cladding Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation20-Apr-202676Total float of 76d exceeds 44 days
A3000Glazing Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation06-Mar-202676Total float of 76d exceeds 44 days
A2990Glazing Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation03-Feb-202676Total float of 76d exceeds 44 days
A3020Exterior Cladding Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation16-Mar-202676Total float of 76d exceeds 44 days
A3030Exterior Cladding Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation13-Apr-202676Total float of 76d exceeds 44 days
A3090Glazing Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation25-Feb-202661Total float of 61d exceeds 44 days
A3100Glazing Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation27-Mar-202661Total float of 61d exceeds 44 days
A3120Exterior Cladding Site Measure and Scanning1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation06-Apr-202661Total float of 61d exceeds 44 days
A3130Exterior Cladding Shop Fabrication1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation04-May-202661Total float of 61d exceeds 44 days
A3200Roof Anchor System Installation1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing19-Jun-202658Total float of 58d exceeds 44 days
A2220Testing and Inspection Cash Allowance Expenditure1.3 Procurement02-Jul-2025316Total float of 316d exceeds 44 days
A2760Masonry Mock-up1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation30-Dec-2025167Total float of 167d exceeds 44 days
A3680Misc. Metals Mock-up1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes23-Apr-202673Total float of 73d exceeds 44 days
A3730Millwork Mock-up1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes25-Jun-202654Total float of 54d exceeds 44 days
A2780Above Grade Vapour Mock-up1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation30-Dec-2025152Total float of 152d exceeds 44 days
A2810Aluminum & Metal Panel Cladding Mock-up1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation16-Mar-202681Total float of 81d exceeds 44 days
A3230Fire Spraying & Intumescent Paint Mock-up1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 125-Feb-202645Total float of 45d exceeds 44 days
A3180Roof Inspection1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing09-Mar-2026101Total float of 101d exceeds 44 days
A2800AVB Inspection1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation30-Dec-2025110Total float of 110d exceeds 44 days
A3080L1, L2 & L3 Air Vapor Barrier Inspection1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation05-Mar-202677Total float of 77d exceeds 44 days
A196023 74 13 - Air Handling Units1.3 Procurement / 1.3.34 Mechanical Equipment15-May-202652Total float of 52d exceeds 44 days
A197023 21 23 - Pumps1.3 Procurement / 1.3.34 Mechanical Equipment12-Jan-202670Total float of 70d exceeds 44 days
A198023 25 00 - Buffer Tanks1.3 Procurement / 1.3.34 Mechanical Equipment24-Dec-202571Total float of 71d exceeds 44 days
A199023 21 16 - Air Separator1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025111Total float of 111d exceeds 44 days
A200023 21 16 - Expansion Tanks1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025111Total float of 111d exceeds 44 days
A201023 57 00 - Heat Exchangers1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025111Total float of 111d exceeds 44 days
A202022 33 00 - Electric Domestic Water Heaters1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025111Total float of 111d exceeds 44 days
A203023 81 26 - Split System1.3 Procurement / 1.3.34 Mechanical Equipment26-Nov-2025101Total float of 101d exceeds 44 days
A204022 13 29 - Sump Pumps1.3 Procurement / 1.3.34 Mechanical Equipment08-Aug-2025177Total float of 177d exceeds 44 days
A207023 00 00 - Exhaust Fans1.3 Procurement / 1.3.34 Mechanical Equipment03-Nov-2025187Total float of 187d exceeds 44 days
A208023 00 00 - Unit Heater1.3 Procurement / 1.3.34 Mechanical Equipment11-Nov-2025112Total float of 112d exceeds 44 days
A210023 00 00 - Wall Fin Heater1.3 Procurement / 1.3.34 Mechanical Equipment18-Dec-202585Total float of 85d exceeds 44 days
A212020 05 10 - Electric Heat Tracing1.3 Procurement / 1.3.34 Mechanical Equipment19-Jan-2026134Total float of 134d exceeds 44 days
A213022 40 00 - Plumbing Fixtures1.3 Procurement / 1.3.34 Mechanical Equipment03-Feb-202654Total float of 54d exceeds 44 days
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment17-Nov-2025108Total float of 108d exceeds 44 days
A219028 31 00 - Fire Alarm1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment27-Oct-2025123Total float of 123d exceeds 44 days
A215026 50 00 - Lighting Fixtures1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment25-Dec-202580Total float of 80d exceeds 44 days
A218026 09 23 - Lighting Control1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment23-Jan-202671Total float of 71d exceeds 44 days
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment14-Apr-202669Total float of 69d exceeds 44 days
217026 50 00 - Emergency Lighting & Exit Signs1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment08-Dec-2025103Total float of 103d exceeds 44 days
A1480.123 00 00 - Exhaust Fans (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings07-Oct-2025248Total float of 248d exceeds 44 days
A1530.120 05 10 - Electric Heat Tracing (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings26-Aug-2025134Total float of 134d exceeds 44 days
A1540.122 40 00 - Plumbing Fixtures (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings11-Sep-202554Total float of 54d exceeds 44 days
A1590.126 09 23 - Lighting Control (R1)1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings02-Sep-202571Total float of 71d exceeds 44 days
A4370Underground Mechanical Installation (DCW, Sprinkler)1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation11-Nov-2025219Total float of 219d exceeds 44 days
A4380Backfilling and Concrete for SOG1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation18-Nov-2025219Total float of 219d exceeds 44 days
A4510Metal Shelving Installation1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation19-Aug-202575Total float of 75d exceeds 44 days
A4560Review Interferences with Steel Joist1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo09-Jul-2025104Total float of 104d exceeds 44 days
A4570Joist Interferences Relocation1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo18-Aug-2025283Total float of 283d exceeds 44 days
A4600Stud Framing1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo23-Jan-2026109Total float of 109d exceeds 44 days
A4610MEP Rough-ins1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo29-Jan-2026109Total float of 109d exceeds 44 days
A4620Plywood Blocking1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo03-Feb-2026109Total float of 109d exceeds 44 days
A4630Drywall Installation1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo06-Feb-2026109Total float of 109d exceeds 44 days
A4640Taping Drywall1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo13-Feb-2026109Total float of 109d exceeds 44 days
A4550Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo20-Jan-2026109Total float of 109d exceeds 44 days
A4660Setup Temporary Hoarding1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area19-Feb-2026109Total float of 109d exceeds 44 days
A4670Electrical and Mechanical Make Safe1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area23-Feb-2026109Total float of 109d exceeds 44 days
A4680Interior Demolition 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area04-Mar-2026109Total float of 109d exceeds 44 days
A4700Review Interferences with Steel Joist1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area11-Aug-202572Total float of 72d exceeds 44 days
A4730Steel Joist Reinforcement Installation1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area24-Oct-202555Total float of 55d exceeds 44 days
A4770Concrete Slab Infill1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)07-Aug-2025135Total float of 135d exceeds 44 days
A4580New Columns Installation1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo02-Oct-202545Total float of 45d exceeds 44 days
A4720Existing Column Reinforcement1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area02-Oct-202555Total float of 55d exceeds 44 days
A4780New Columns Installation1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)14-Aug-2025135Total float of 135d exceeds 44 days
A4790Existing Column Reinforcement1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)21-Aug-2025135Total float of 135d exceeds 44 days
A4800Flatness Survey @ Floor Slab1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)25-Aug-2025135Total float of 135d exceeds 44 days
A4810Self Levelling1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1)04-Sep-2025135Total float of 135d exceeds 44 days
A2090xMetal Shelving1.3 Procurement14-Aug-202575Total float of 75d exceeds 44 days
A4650Painting1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo18-Feb-2026109Total float of 109d exceeds 44 days
A4690Electrical Fixtures1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area11-Mar-2026109Total float of 109d exceeds 44 days
A4710Relocation of Interferences1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area25-Aug-202572Total float of 72d exceeds 44 days
A2550xR6 - RFI 60 Sprinkler Diesel Pump 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)21-Oct-2025219Total float of 219d exceeds 44 days
A1380xMetal Shelving (R1)1.2 Shop Drawings16-Jul-202575Total float of 75d exceeds 44 days
A2560xR7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)13-Aug-202565Total float of 65d exceeds 44 days
A1460.123 25 00 - Water Treatment (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings17-Sep-202550Total float of 50d exceeds 44 days
A205023 25 00 - Water Treatment1.3 Procurement / 1.3.34 Mechanical Equipment09-Feb-202650Total float of 50d exceeds 44 days
A2420Form and Pour North Exit Stair1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work05-Sep-2025119Total float of 119d exceeds 44 days
A2480Concrete for Remaining Pad Footings (Ramp)1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work03-Jul-2025315Total float of 315d exceeds 44 days
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion. Full paths are in the tooltip and the CSV export.
C8High Duration Register, all flagged activities
38 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A3850Foundations1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction23-Feb-2026Duration (d): 116Duration of 116d exceeds 44 days
A1710Misc. Metals 1.3 Procurement27-Jan-2026Duration (d): 80Duration of 80d exceeds 44 days
A1720Millwork 1.3 Procurement09-Oct-2025Duration (d): 51Duration of 51d exceeds 44 days
A1760Exterior Wall Cladding1.3 Procurement01-Dec-2025Duration (d): 60Duration of 60d exceeds 44 days
A1800Interior Aluminum Screens1.3 Procurement29-Dec-2025Duration (d): 90Duration of 90d exceeds 44 days
A1810Flush Wood Doors 1.3 Procurement12-Dec-2025Duration (d): 75Duration of 75d exceeds 44 days
A1820Coiling Doors1.3 Procurement14-Jan-2026Duration (d): 100Duration of 100d exceeds 44 days
A1830Aluminum Framed Glazing Systems1.3 Procurement28-Nov-2025Duration (d): 80Duration of 80d exceeds 44 days
A1840Finished Hardware 1.3 Procurement05-Dec-2025Duration (d): 91Duration of 91d exceeds 44 days
A1890Flooring 1.3 Procurement24-Oct-2025Duration (d): 61Duration of 61d exceeds 44 days
A1920Fall Arrest Anchors and Horizontal Lines1.3 Procurement23-Dec-2025Duration (d): 60Duration of 60d exceeds 44 days
A1930Hydraulic Lift 1.3 Procurement01-Dec-2025Duration (d): 101Duration of 101d exceeds 44 days
A2210Landscape (unit pavers, furniture, etc)1.3 Procurement31-Oct-2025Duration (d): 60Duration of 60d exceeds 44 days
A1790Hollow Metal Doors1.3 Procurement24-Oct-2025Duration (d): 61Duration of 61d exceeds 44 days
A195023 82 19 - Fan Coil Units1.3 Procurement / 1.3.34 Mechanical Equipment25-Feb-2026Duration (d): 109Duration of 109d exceeds 44 days
A196023 74 13 - Air Handling Units1.3 Procurement / 1.3.34 Mechanical Equipment15-May-2026Duration (d): 180Duration of 180d exceeds 44 days
A197023 21 23 - Pumps1.3 Procurement / 1.3.34 Mechanical Equipment12-Jan-2026Duration (d): 100Duration of 100d exceeds 44 days
A198023 25 00 - Buffer Tanks1.3 Procurement / 1.3.34 Mechanical Equipment24-Dec-2025Duration (d): 120Duration of 120d exceeds 44 days
A199023 21 16 - Air Separator1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A200023 21 16 - Expansion Tanks1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A201023 57 00 - Heat Exchangers1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A202022 33 00 - Electric Domestic Water Heaters1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A203023 81 26 - Split System1.3 Procurement / 1.3.34 Mechanical Equipment26-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A206023 37 13 - Diffuser and Grilles1.3 Procurement / 1.3.34 Mechanical Equipment05-Mar-2026Duration (d): 100Duration of 100d exceeds 44 days
A207023 00 00 - Exhaust Fans1.3 Procurement / 1.3.34 Mechanical Equipment03-Nov-2025Duration (d): 72Duration of 72d exceeds 44 days
A208023 00 00 - Unit Heater1.3 Procurement / 1.3.34 Mechanical Equipment11-Nov-2025Duration (d): 78Duration of 78d exceeds 44 days
A209023 52 16 - Heating Boilers1.3 Procurement / 1.3.34 Mechanical Equipment16-Mar-2026Duration (d): 100Duration of 100d exceeds 44 days
A210023 00 00 - Wall Fin Heater1.3 Procurement / 1.3.34 Mechanical Equipment18-Dec-2025Duration (d): 90Duration of 90d exceeds 44 days
A211023 74 13 - Air Source Heat Pump1.3 Procurement / 1.3.34 Mechanical Equipment05-Jun-2026Duration (d): 224Duration of 224d exceeds 44 days
A212020 05 10 - Electric Heat Tracing1.3 Procurement / 1.3.34 Mechanical Equipment19-Jan-2026Duration (d): 100Duration of 100d exceeds 44 days
A213022 40 00 - Plumbing Fixtures1.3 Procurement / 1.3.34 Mechanical Equipment03-Feb-2026Duration (d): 100Duration of 100d exceeds 44 days
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment17-Nov-2025Duration (d): 90Duration of 90d exceeds 44 days
A219028 31 00 - Fire Alarm1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment27-Oct-2025Duration (d): 90Duration of 90d exceeds 44 days
A215026 50 00 - Lighting Fixtures1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment25-Dec-2025Duration (d): 90Duration of 90d exceeds 44 days
A218026 09 23 - Lighting Control1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment23-Jan-2026Duration (d): 100Duration of 100d exceeds 44 days
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment14-Apr-2026Duration (d): 183Duration of 183d exceeds 44 days
217026 50 00 - Emergency Lighting & Exit Signs1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment08-Dec-2025Duration (d): 90Duration of 90d exceeds 44 days
A205023 25 00 - Water Treatment1.3 Procurement / 1.3.34 Mechanical Equipment09-Feb-2026Duration (d): 100Duration of 100d exceeds 44 days
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion. Full paths are in the tooltip and the CSV export.
C9Valid Dates Register, all flagged activities
103 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
217026 50 00 - Emergency Lighting & Exit Signs1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment08-Dec-2025Actual start (2025-07-30) after status date (2025-07-01)
A1060Foundation Concrete Rebar Shop Drawing1.2 Shop Drawings08-Jul-2025Actual finish (2025-07-08) after status date (2025-07-01)
A1080Bentonite Waterstop Data Sheet1.2 Shop Drawings02-Jul-2025Actual finish (2025-07-02) after status date (2025-07-01)
A1090Masonry and Mortar Samples & Data Sheets1.2 Shop Drawings18-Aug-2025Actual finish (2025-08-18) after status date (2025-07-01)
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)1.2 Shop Drawings14-Jul-2025Actual finish (2025-07-14) after status date (2025-07-01)
A1100.1Structural Steel Framing and Steel Deck Shop Drawings (R1)1.2 Shop Drawings25-Aug-2025Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-25) after status date (2025-07-01)
A1100.2Structural Steel Framing and Steel Deck Shop Drawings (R2)1.2 Shop Drawings04-Sep-2025Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
A1110Structural Reinforcement + Decking Shop Drawings1.2 Shop Drawings01-Aug-2025Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-01) after status date (2025-07-01)
A1120Cold-formed Metal Framing Shop Drawings1.2 Shop Drawings23-Jul-2025Actual finish (2025-07-23) after status date (2025-07-01)
A1130Misc. Metals Shop Drawings1.2 Shop Drawings02-Oct-2025Actual start (2025-08-26) after status date (2025-07-01)
A1150Built-up Roofing Shop Drawings1.2 Shop Drawings09-Jul-2025Actual finish (2025-07-09) after status date (2025-07-01)
A1160TPO Roofing Shop Drawings1.2 Shop Drawings26-Aug-2025Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-26) after status date (2025-07-01)
A1180Exterior Wall Cladding Shop Drawings1.2 Shop Drawings05-Sep-2025Actual start (2025-08-11) after status date (2025-07-01)
A1190Fire-resistive Material Data Sheet1.2 Shop Drawings09-Jul-2025Actual finish (2025-07-09) after status date (2025-07-01)
A1210Interior Aluminum Screen1.2 Shop Drawings20-Aug-2025Actual start (2025-07-25) after status date (2025-07-01)
A1220Flush Wood Doors Sample1.2 Shop Drawings27-Aug-2025Actual start (2025-08-26) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01)
A1230Coiling Doors1.2 Shop Drawings21-Aug-2025Actual start (2025-08-05) after status date (2025-07-01) | Actual finish (2025-08-21) after status date (2025-07-01)
A12380.123 21 23 - Pumps (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings19-Aug-2025Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-19) after status date (2025-07-01)
A1280ACT Data sheet and Sample1.2 Shop Drawings27-Aug-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01)
A1280.1ACB Data sheet and Sample1.2 Shop Drawings04-Sep-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
A1290Suspended Metal Soffits1.2 Shop Drawings04-Sep-2025Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
A1330Fall Arrest Anchors and Horizontal Lines1.2 Shop Drawings29-Sep-2025Actual start (2025-08-14) after status date (2025-07-01)
A1340Hydraulic Lift Shop Drawings1.2 Shop Drawings09-Jul-2025Actual finish (2025-07-09) after status date (2025-07-01)
A136023 82 19 - Fan Coil Units (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A1360.123 82 19 - Fan Coil Units (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01)
A1360.223 82 19 - Fan Coil Units (R2)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings19-Sep-2025Actual start (2025-08-25) after status date (2025-07-01)
A137023 74 13 - Air Handling Units (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings21-Jul-2025Actual finish (2025-07-21) after status date (2025-07-01)
A1370,123 74 13 - Air Handling Units (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings28-Aug-2025Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01)
A138023 21 23 - Pumps (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings04-Jul-2025Actual finish (2025-07-04) after status date (2025-07-01)
A139023 25 00 - Buffer Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A140023 21 16 - Air Separator1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A141023 21 16 - Expansion Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A142023 57 00 - Heat Exchangers1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A143022 33 00 - Electric Domestic Water Heaters1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Actual finish (2025-07-03) after status date (2025-07-01)
A146023 25 00 - Water Treatment (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Actual finish (2025-08-12) after status date (2025-07-01)
A1460.123 25 00 - Water Treatment (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings17-Sep-2025Actual start (2025-08-22) after status date (2025-07-01)
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings14-Aug-2025Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01)
A1470.123 37 13 - Diffuser and Grilles Shop Drawings (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings09-Oct-2025Actual start (2025-09-05) after status date (2025-07-01)
A1480.123 00 00 - Exhaust Fans (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings07-Oct-2025Actual start (2025-09-16) after status date (2025-07-01)
A150023 52 16 - Heating Boilers1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings21-Oct-2025Actual start (2025-09-12) after status date (2025-07-01)
A151023 00 00 - Wall Fin Heater1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01)
A153020 05 10 - Electric Heat Tracing (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings12-Aug-2025Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01)
A154022 40 00 - Plumbing Fixtures (R0)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings31-Jul-2025Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-31) after status date (2025-07-01)
A1540.122 40 00 - Plumbing Fixtures (R1)1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings11-Sep-2025Actual start (2025-08-14) after status date (2025-07-01)
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings08-Jul-2025Actual finish (2025-07-08) after status date (2025-07-01)
A156026 50 00 - Emergency Lighting & Exit Signs1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings29-Jul-2025Actual finish (2025-07-29) after status date (2025-07-01)
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings22-Jul-2025Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01)
A158026 50 00 - Lighting Fixtures1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings18-Aug-2025Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01)
A159026 09 23 - Lighting Control (R0)1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings18-Aug-2025Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01)
A1660Bentonite Waterstop 1.3 Procurement09-Jul-2025Actual start (2025-07-03) after status date (2025-07-01) | Actual finish (2025-07-09) after status date (2025-07-01)
A1680Structural Steel 1.3 Procurement01-Oct-2025Actual start (2025-09-04) after status date (2025-07-01)
A198023 25 00 - Buffer Tanks1.3 Procurement / 1.3.34 Mechanical Equipment24-Dec-2025Actual start (2025-07-04) after status date (2025-07-01)
A199023 21 16 - Air Separator1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Actual start (2025-07-04) after status date (2025-07-01)
A200023 21 16 - Expansion Tanks1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Actual start (2025-07-04) after status date (2025-07-01)
A201023 57 00 - Heat Exchangers1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Actual start (2025-07-04) after status date (2025-07-01)
A202022 33 00 - Electric Domestic Water Heaters1.3 Procurement / 1.3.34 Mechanical Equipment12-Nov-2025Actual start (2025-07-04) after status date (2025-07-01)
A203023 81 26 - Split System1.3 Procurement / 1.3.34 Mechanical Equipment26-Nov-2025Actual start (2025-07-10) after status date (2025-07-01)
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment17-Nov-2025Actual start (2025-07-09) after status date (2025-07-01)
A215026 50 00 - Lighting Fixtures1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment25-Dec-2025Actual start (2025-08-19) after status date (2025-07-01)
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment14-Apr-2026Actual start (2025-07-23) after status date (2025-07-01)
A2280Under Pinning Inspection1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works14-Jul-2025Actual finish (2025-07-14) after status date (2025-07-01)
A2290Existing Structure Under Pinning1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works15-Jul-2025Actual finish (2025-07-15) after status date (2025-07-01)
A2350Daylighting of Existing Hydro Ductbank & Services1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works07-Jul-2025Actual finish (2025-07-07) after status date (2025-07-01)
A2360Ductbank Shoring 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works08-Jul-2025Actual finish (2025-07-08) after status date (2025-07-01)
A2370Bulk Excavation to U/S of Footings1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work22-Jul-2025Actual start (2025-07-16) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01)
A2380Bulk Excavation to U/S North Stair Footing1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work23-Jul-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01)
A2390Subgrade Inspection1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work22-Jul-2025Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01)
A2400Subgrade Preparation1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work23-Jul-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01)
A2410Soil Bearing Capacity Inspection1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work24-Jul-2025Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01)
A2410xRFI #17 Demo Clarification1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification11-Jul-2025Actual finish (2025-07-11) after status date (2025-07-01)
A2420Form and Pour North Exit Stair1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work05-Sep-2025Actual start (2025-08-04) after status date (2025-07-01)
A2420xPC-002 Demo Clarification Issuance1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification14-Jul-2025Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01)
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work23-Jul-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01)
A2430xPCO-008 (Quote) Submission1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification24-Jul-2025Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01)
A2440xCO-005 Issuance 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification07-Aug-2025Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-08-07) after status date (2025-07-01)
A2450Rebar for Pad Footings1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work24-Jul-2025Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01)
A2450xCD-01 Water Room Demo (Elec. FACP) Issuance1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification18-Jul-2025Actual start (2025-07-18) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01)
A2460Rebar Inspection1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work25-Jul-2025Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-07-25) after status date (2025-07-01)
A2460xCD-01 Fire Alarm Panel Relocation1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification24-Jul-2025Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01)
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work28-Jul-2025Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01)
A2470xWater Room Block Wall Demo1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification12-Aug-2025Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01)
A2480xExisting Vestibule Slab Cutting1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification13-Aug-2025Actual start (2025-08-13) after status date (2025-07-01) | Actual finish (2025-08-13) after status date (2025-07-01)
A2490Concrete Field Testing1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work28-Jul-2025Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01)
A2490xExisting Vestibule Slab Removal1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification14-Aug-2025Actual start (2025-08-14) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01)
A2500Install Rebar for Piers1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work08-Sep-2025Actual start (2025-07-29) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01)
A2500xR1 - RFI #19 & 20 - Existing DCW and Sanitary Line1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)27-Aug-2025Actual finish (2025-08-27) after status date (2025-07-01)
A2510Supply of Embedment & Ankors1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work22-Aug-2025Actual start (2025-08-22) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01)
A2520Form and Pour Foundation Piers1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work08-Sep-2025Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01)
A2520xR3 - RFI 45 - City of Barrie Water Department - Request to Review Drawings1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)04-Sep-2025Actual start (2025-07-31) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
A2530Backfilling to U/S of Grade Beams1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work12-Sep-2025Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-12) after status date (2025-07-01)
A2530xR4 - PC-004 Grade Beam Rebar1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)10-Sep-2025Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-09-10) after status date (2025-07-01)
A2540xR5 - RFI #39R2 Jewelery Workshop Interior Fitout1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)04-Sep-2025Actual start (2025-07-17) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
A2550xR6 - RFI 60 Sprinkler Diesel Pump 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK)21-Oct-2025Actual start (2025-08-21) after status date (2025-07-01)
A2600Compaction Inspection1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work15-Aug-2025Actual start (2025-08-15) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01)
A3920Setup Temporary Hoarding1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation04-Jul-2025Actual start (2025-07-04) after status date (2025-07-01) | Actual finish (2025-07-04) after status date (2025-07-01)
A3930Interior Demolition1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation02-Sep-2025Actual start (2025-07-21) after status date (2025-07-01) | Actual finish (2025-09-02) after status date (2025-07-01)
A3960Vinyl Flooring Abatement (Cash Allowance)1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation11-Jul-2025Actual start (2025-07-07) after status date (2025-07-01) | Actual finish (2025-07-11) after status date (2025-07-01)
A4340Electrical and Mechanical Make Safe1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation18-Jul-2025Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01)
A4390Review Interferences with Steel Joist1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation15-Aug-2025Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01)
A4410Joist Interferences Relocation1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation22-Aug-2025Actual start (2025-08-16) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01)
A5070Removal of Existing Water and Sanitary1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work14-Jul-2025Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01)
A5220Weather Impact (Rain) - August 28, 20251.4.5 Building F Expansion / 1 Phase 2 - Foundation Work28-Aug-2025Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01)
A5250Weather Impact (Rain) - September 04, 20251.4.5 Building F Expansion / 1 Phase 2 - Foundation Work04-Sep-2025Actual start (2025-09-04) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01)
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion. Full paths are in the tooltip and the CSV export.
C11Missed Tasks Register, all flagged activities
38 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A3780Layout for Elevator Cylinder1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator23-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-19)
A3790Drilling Elevator Cylinder from Grade1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator24-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-20)
A3800Install Steel Casing into the ground1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator25-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-23)
A1110Structural Reinforcement Shop Drawings1.2 Shop Drawings01-Aug-2025Working days late: 30 wdActual finish 30 wd later than baseline (2025-06-19)
A2220Testing and Inspection Cash Allowance Expenditure1.3 Procurement02-Jul-2025Working days late: 34 wdForecast finish 34 wd later than baseline (2025-05-13)
A2280Under Pinning Inspection1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works14-Jul-2025Working days late: 15 wdActual finish 15 wd later than baseline (2025-06-20)
A139023 25 00 - Buffer Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Working days late: 3 wdActual finish 3 wd later than baseline (2025-06-27)
A140023 21 16 - Air Separator1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Working days late: 3 wdActual finish 3 wd later than baseline (2025-06-27)
A141023 21 16 - Expansion Tanks1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Working days late: 3 wdActual finish 3 wd later than baseline (2025-06-27)
A142023 57 00 - Heat Exchangers1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings03-Jul-2025Working days late: 5 wdActual finish 5 wd later than baseline (2025-06-25)
A2510Supply of Embedment & Ankors1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work22-Aug-2025Working days late: 44 wdActual finish 44 wd later than baseline (2025-06-20)
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings08-Jul-2025Working days late: 9 wdActual finish 9 wd later than baseline (2025-06-24)
A159026 09 23 - Lighting Control1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings18-Aug-2025Working days late: 36 wdActual finish 36 wd later than baseline (2025-06-26)
A2240Construction Site Setup. Fencing and Temp Facilities1.4 Construction16-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-12)
A1040Permit (Not Required Per Ontario Community College)1.1 Preconstruction16-May-2025Working days late: 3 wdActual finish 3 wd later than baseline (2025-05-13)
A1010Contract Award1.1 Preconstruction02-May-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-04-30)
A1030IFC Drawings Released1.1 Preconstruction15-May-2025Working days late: 3 wdActual finish 3 wd later than baseline (2025-05-12)
A1060Foundation Concrete Rebar Shop Drawing1.2 Shop Drawings08-Jul-2025Working days late: 12 wdActual finish 12 wd later than baseline (2025-06-19)
A2230Ontario Community College Auto Show1.4 Construction09-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-05)
A2270Excavation for Under Pinning1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works23-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-19)
A2250Tree Removal, Protection and Equipment Mobilization1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works17-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-13)
A2260Top Soil Stripping1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works20-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-18)
A2300Setup Hoarding @ Vestibule F1001.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works18-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-16)
A2310Relocate FAA1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works17-Jun-2025Working days late: 1 wdActual finish 1 wd later than baseline (2025-06-16)
A2320Demolition of Existing Vestibule F1001.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works25-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-23)
A2330Gas Meter and Pipe Relocation Investigation1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works19-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-17)
A2340Gas Meter and pipe Relocation1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works23-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-06-19)
A1020Subcontract Award1.1 Preconstruction02-Jun-2025Working days late: 2 wdActual finish 2 wd later than baseline (2025-05-29)
A3920Setup Hoarding at Existing Areas1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation04-Jul-2025Working days late: 14 wdActual finish 14 wd later than baseline (2025-06-13)
A3940Existing Slab Removal and Trenching1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation28-Oct-2025Working days late: 90 wdForecast finish 90 wd later than baseline (2025-06-19)
A1050Ductbank Underpinning Drawing1.2 Shop Drawings30-Jun-2025Working days late: 12 wdActual finish 12 wd later than baseline (2025-06-12)
A1070Foundation Concrete Mix Design1.2 Shop Drawings25-Jun-2025Working days late: 4 wdActual finish 4 wd later than baseline (2025-06-19)
A1100Structural Steel Framing and Steel Deck Shop Drawings1.2 Shop Drawings14-Jul-2025Working days late: 16 wdActual finish 16 wd later than baseline (2025-06-19)
A1120Cold-formed Metal Framing Shop Drawings1.2 Shop Drawings23-Jul-2025Working days late: 23 wdActual finish 23 wd later than baseline (2025-06-19)
A1080Bentonite Waterstop Data Sheet1.2 Shop Drawings02-Jul-2025Working days late: 8 wdActual finish 8 wd later than baseline (2025-06-19)
A1160TPO Roofing Shop Drawings1.2 Shop Drawings26-Aug-2025Working days late: 47 wdActual finish 47 wd later than baseline (2025-06-19)
A1650Foundation Concrete Mix Design1.3 Procurement27-Jun-2025Working days late: 4 wdActual finish 4 wd later than baseline (2025-06-23)
A1660Bentonite Waterstop 1.3 Procurement09-Jul-2025Working days late: 8 wdActual finish 8 wd later than baseline (2025-06-26)
WBS shown relative to the common root: Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion. Full paths are in the tooltip and the CSV export.
A-06b

Detailed Comparison

baseline → current → variance
MetricBaselineCurrentVariance
Total Tasks327405+78
Project Finish31-Aug-202630-Sep-2026+21 WD
Project Start01-Apr-202501-Apr-20250 WD
CPLI0.93below 1.0
BEI0.58below 0.95
A-07

Schedule Exposure

measured figures only · derivations below
Finish Drift
+21 WD
current forecast finish vs baseline finish
CPLI
0.93
critical path length index (C13)
BEI
0.58
baseline execution index (C14)
Drift Direction
Slipping
sign of the finish drift
How each figure is derived
  • Finish drift: working days from the baseline finish (31-Aug-2026) to the current forecast finish (30-Sep-2026), counted on the project calendar. Positive = finishing later than baseline.
  • CPLI 0.93: (contract finish − data date) ÷ (forecast finish − data date). Below 1.00 = the forecast finish falls beyond the contract finish. Here: contract finish 31-Aug-2026, forecast finish 30-Sep-2026, measured from the data date 01-Jul-2025.
  • BEI 0.58: baseline activities actually complete ÷ baseline activities planned complete at the data date. Below 1.00 = executing behind the baseline plan. Here: 25 complete ÷ 43 planned complete at the data date.
  • Drift direction: the sign of the finish drift. Positive drift (+21 WD), so the schedule is slipping against baseline.
  • No resource figure is reported. The schedule carries no resource assignments (C10 not scored), so no resource-based risk or resource-increase percentage can be derived from this file.
A-08

Schedule Forecast

forward-pass dates as scheduled
Forecasted Completion
schedule forward-pass finish
Baseline Completion
baseline schedule finish
Variance
+21 WD
working days, forecast vs baseline
Data Date
status date of the current update
Basis
  • These are the schedule’s own dates as read from the file: the forecast completion is the current schedule’s forward-pass finish, not a probabilistic projection. This screen models no delay probabilities and no resource requirements; a probabilistic finish-date forecast requires a schedule risk analysis (Monte Carlo), which is a separate deliverable.
A-09

Strategic Recommendations

prioritized remediation · 8 failing criteria
01Valid Dates (C9)Priority · Critical
Immediate Action Required. Activities with invalid actual or forecast dates. Run Tools > Schedule with the Date Check option on. Look for Actual Start or Actual Finish AFTER the data date, that's a data-entry error 100% of the time.
02Missed Tasks (C11)Priority · High
High Priority Actions. Activities that should have finished by the data date and did not. Show the Baseline Finish column and filter for Baseline Finish on or before the Data Date. Per DCMA-EA PAM 200.1 §4.11 this is a finish test; start dates are not part of it.
03CPLI (C13)Priority · High
High Priority Actions. CPLI below the 0.95 DCMA investigation flag. Recalculate: CPLI = (Critical Path Length + Total Float) ÷ Critical Path Length. Below 1.00 the path carries no margin; DCMA-EA PAM 200.1 §3.1.2.3 raises the investigation flag below 0.95.
04BEI (C14)Priority · High
High Priority Actions. BEI below 0.95, falling behind baseline pace. Recalculate: BEI = (Activities Actually Finished by Data Date) ÷ (Activities Baselined to Finish by Data Date). Below 0.95 = trending late.
05Leads (C2)Priority · Medium
Recommended Actions. Negative-lag (lead) relationships. Filter the relationship view for Lag < 0 (in P6: Activities > Relationships > group/sort by Lag).
06Lags (C3)Priority · Medium
Recommended Actions. Excessive lags on relationships. Filter relationships for Lag > 0 working days. Bucket them by intent: cure time, procurement, owner approvals, design review, transport.
07High Float (C6)Priority · Optimize
Optimization Opportunities. Activities with > 44 days of total float. Sort the activity list by Total Float descending. Anything over 44 working days needs scrutiny.
08High Duration (C8)Priority · Optimize
Optimization Opportunities. Activities longer than 44 working days. Sort by Original Duration descending. Anything over 44 working days gets a hard look.
PathPath Back to Green, grade re-scored per cleared criterion
current: Grade F · 38% · RED
Criterion clearedCurrent metricGradeComplianceBand
C9 Valid Dates103D46%RED
C11 Missed Tasks38D46%RED
C13 CPLI0.93D46%RED
C14 BEI0.58D46%RED
C2 Leads7D46%RED
C3 Lags10.6%D46%RED
C6 High Float53% (152)D46%RED
C8 High Duration13.2% (38)D46%RED
All 8 failing criteria clearedA100%GREEN
How these grades are computed
  • The grade is a pure function of the pass rate: passed ÷ scored, graded A ≥90%, B ≥75%, C ≥60%, D ≥45%, else F, the same scoring the headline grade uses. Each row adds exactly one cleared criterion to the 5 currently passing of 13 scored.
  • Clearing a criterion means correcting its listed activities so the check passes (for example, clearing C9 means fixing every invalid date in its register). Other criteria are held at their computed results; knock-on effects of the corrections themselves are not modelled here.
A-10

Report Information

provenance & reproducibility
Generated
2026-09-01T09:02Z
Source Schedule
Ontario_Community_College_current.xer
Engine
Schedule Health Dashboard v2.0 · cpm-engine v2.9.42
Baseline
01-Apr-2025
Standard
DCMA 14-Point Assessment
Data Date
01-Jul-2025
Current XER SHA-256
7ed1cd8309b1752af74ec9c8d2fa11fbc9a58d4e065630a2589809ed3780ca10
Baseline XER SHA-256 (Ontario_Community_College_baseline.xer)
37a454edfda707d797f2dab200919c1da729a17454e53b46084b6a17bc4819db

Analyst conclusion and next step

What this schedule can and cannot prove

Delay investigation warranted

The finish has moved materially and the movement deserves a proper look at the update chain before anyone takes a position. The posted Preliminary Assessment is the next step.

Technical condition: the assessment grades this schedule F · 38% · RED; the forecast finish has moved 21 working days later than the baseline.

The movement is material and this pair of files cannot yet explain it. The forecast completion has moved 21 working days later than the baseline, and the schedule itself grades F on the DCMA screen, so both the dates and the instrument that produced them need attention before anyone takes a position.

A baseline and one update are endpoints. The causation story lives in the monthly chain between them and in the project record, and on this file only a minority of the moved activities have evidence artifacts paired to them. Examining the chain is the correct next step, and it is a bounded piece of work.

The findings that actually matter

1The forecast completion moved 21 working days later than the baseline, to 30-Sep-2026.
2The schedule grades F (38%) on the DCMA-14 screen, driven by high float on 53% of activities and 103 activities with invalid dates: the instrument needs repair alongside the delay question.
3Only 10.3% of the positive slips are evidence-supported in the records provided, so causation is asserted, not yet shown.

Evidence still required

The full monthly update chain (every XER between baseline and current, not just the endpoints)
Contract milestone dates and any amendments to them
Delay notices and the contractual notice log
Change orders and change directives with dates
Contemporaneous correspondence for the affected work fronts

The next step, precisely

The posted Preliminary Assessment ($5,000 to $8,500 CAD, fixed fee quoted before work starts) would cover:

1.Ingest the full monthly update chain and rebuild the 21 working days of movement window by window on the project calendars.
2.Attribute each driving window to its cause using the schedule record and the documents listed above.
3.Screen the chain for baseline changes, logic revisions and calendar edits that move dates without progress.
4.Report whether a delay position is supportable, in which direction, and what a full analysis would cost if warranted.

Conclusion written by Dana Fitkowski, Principal, Critical Path Partners on 2026-09-01. The engine produced the files; the analyst produced this conclusion.

Generated 2026-09-01T09:02Z  ·  Source: Ontario_Community_College_current.xer  ·  Grade F · 38% · RED  ·  Schedule Health Dashboard v2.0 · cpm-engine v2.9.42DCMA 14-Point Assessment · Automated screening